The work consists of construction of the following improvements:
• Approximately 700 feet of 24-inch water line
• Approximately 371 feet of 8-inch water line
• Approximately 110 feet of 10-inch water line
• Pump station including two vertical turbine, 25-HP pumps
• Block building
• Electrical controls and instrumentation
• Pipes, valves, meters, and appurtenances complete